Renovation and Line Marking at Outwood Academy Normanby

Outwood Academy Normanby

February 2024

Outwood Academy Normanby

February 2024

GL Floors Machine sanded the existing Games Hall hardwood floor taking it back to the bare wood, upon completion of the sanding works the flooring was then applied with 1 coat of Junckers SB Primer, followed by 3 coats of Junckers HT700 Commercial lacquer,

After completion of the second coat of Junckers HT700 Commercial lacquer, M&M Markings marked out and applied the following line markings:

  • 4 No. Badminton Courts
  • 1 No. Basketball Court
  • 1 No. Volleyball Court
  • 1 No. Netball Court
  • 1 No. Tennis Court
  • 1 No. 5-a-Side Pitch

All sanding and line marking works were completed in 7 days